Granite State Gas Transmission, Inc.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/07/2020, Docket: RS93- 1-001, Status: Accepted
Original Sheet No. 240 Original Sheet No. 240 : Effective
GENERAL TERMS AND CONDITIONS
(continued)
20. FLOW THROUGH OF FIXED TAKE-OR-PAY CHARGES FROM ALGONQUIN GAS
TRANSMISSION COMPANY
20.1 Purpose
This Article establishes the procedures under which
Transporter shall recover from its customers the total
Take-or-Pay charges approved by the FERC to be collected
from Transporter by Algonquin Gas Transmission Company
("Algonquin") related to the flow through of Take-or-Pay
charges assessed Algonquin by its upstream pipeline
suppliers, CNG Transmission Corporation (CNGT), and
National Fuel Gas Supply Corporation (National). Such
charges by Transporter shall be paid by Shipper until
Transporter has recovered from each Shipper the total
aggregate allocated amounts, principal and carrying
charges, pursuant to this Article. Such charges exclude
any transition cost arising under Order No. 636.
20.2 Basis for the Flow Through of Take-or-Pay Surcharge
The fixed Take-or-Pay Charges as described below shall
be flowed through to each of Transporter's customers, as
applicable, on an as-billed basis in accordance with the
allocated costs as set forth on Tariff Sheet No. 26.
The methods for allocating costs mirror the methodolo-
gies utilized by Algonquin in flowing through its Take-
or-Pay costs from CNGT and National, with 50% of such
small customers allocated amount being reallocated to
Transporter's remaining customers.
(a) Take-or-Pay Surcharges Related to CNG Transmission
The total and monthly charges permitted by the
FERC to be collected by Algonquin from Transport-
er, attributable to the flow through by