-- M O N T H L Y C H A R G E S --
Month Bay State Northern Total
March 1994 $713 $162 $875
April $713 $162 $875
May $713 $162 $875
June $713 $162 $875
July $713 $162 $875
August $713 $162 $875
September $713 $162 $875
October $713 $162 $875
November $713 $162 $875
December $713 $162 $875
January 1995 $713 $162 $875
February $713 $162 $875
TOTAL $8,556 $1,944 $10,500
________________
The monthly amounts reflect a summary of the Order 636 related
charges to be billed by Algonquin over the twelve month period March
1994 - February 1995, pursuant to its FERC Gas Tariff, Fourth
Revised Volume No. 1 and are subject to carrying charges calculated
pursuant to the Commission's Regulations. Customers may elect to
pay their share of the outstanding balance of Algonquin's charges in
a lump sum payment.