Guardian Pipeline, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2010, Docket: RP10-926-000, Status: Effective
First Revised Sheet No. 206 First Revised Sheet No. 206
Superseding: Original Sheet No. 206
GENERAL TERMS AND CONDITIONS
(Continued)
27. POLICY WITH RESPECT TO FEES AND CONSTRUCTION OF LATERAL, DELIVERY
AND RECEIPT FACILITIES (Continued)
hourly, daily, monthly and annual quantities of the
service that supports the new interconnect and such
other data as is reasonably required to construct the
interconnect facility;
(e) The new interconnect must not result in any minimum
pressure receipt or delivery requirement by
Transporter. Transporter shall not be responsible for
any downstream parties' facilities, the operation or
maintenance of such facilities, or the delivery of any
unauthorized quantities to the facilities;
(f) The service supporting the interconnect as well as the
construction of the new facilities must conform with
the provisions of Transporter's FERC Gas Tariff as
well as applicable regulatory requirements;
(g) The proposed interconnect must not cause Transporter
to be in violation of any applicable environmental or
safety laws or regulations with respect to the
facilities required to establish an interconnect with
Transporter's existing facilities; and
(h) The proposed interconnect must not cause Transporter
to be in violation of its right-of-way agreements or
any other contractual obligations with respect to the
interconnect facilities.
27.2 Laterals And Other Facilities
Except as to Section 27.1, unless otherwise agreed
to by the parties, Transporter shall not be required
to own, construct or install and/or operate any
facilities to perform any service requested by a