27. POLICY WITH RESPECT TO FEES AND CONSTRUCTION OF LATERAL,
DELIVERY AND RECEIPT FACILITIES
27.1 Meters and Taps At Point(s) Of Receipt And Point(s) Of
Delivery
If requested by a Shipper, Transporter agrees to own,
construct and install and/or operate new meters and
taps and associated facilities at Point(s) of Receipt
and Point(s) of Delivery only if the cost of such
meters, taps and associated facilities are paid for by
Shipper and/or a third party on a payment basis
mutually agreed to by such Shipper and Transporter in
advance and in writing. Such request, if granted,
shall not cause Shipper's reservation charges paid to
Transporter to decrease.
In addition to the above requirements, Transporter
will agree to construct a new interconnect or modify an
existing interconnect on the following terms:
(a) The construction of the new interconnect will not
create any significant operational problems for
Transporter;
(b) The proposed interconnect will not adversely
affect existing service or adversely alter the
operation of the pipeline system;
(c) The new interconnect must be at a mutually
agreeable location on Transporter's system;
provided, however, that Transporter may not deny
a customer's request for specific placement of
the interconnect without adequate operational,
environmental, or legal justification;
(d) In order to properly and prudently design and
size the new interconnect, Transporter must be
provided with reasonable and reliable data
concerning the interconnecting facilities,
including delivery pressures, and anticipated