Guardian Pipeline, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/2002, Docket: RP02-534-000, Status: Effective
Original Sheet No. 200 Original Sheet No. 200 : Superseded
GENERAL TERMS AND CONDITIONS
(Continued)
24. FORCE MAJEURE (Continued)
dispatch, although this provision shall not be
construed to impose liability beyond that to which a
party may otherwise be subject and this provision is
subject to other sections of these GT&C with respect
to limitations on liability; provided further, such
causes or contingencies affecting performance shall
not relieve a party from its obligation to make
payments of any and all amounts owed or coming due
under Shipper's applicable Service Agreement during
the period of the Force Majeure.
24.4 Compliance with Directives of Governmental Agencies
Whenever, in order to comply with orders, directives,
or regulations of duly constituted state, local, or
federal authorities, including but not limited to the
Department of Transportation, FERC, and the
Environmental Protection Agency, Transporter must
curtail deliveries to or for the account of Shipper
and is unable to deliver to or for the account of
Shipper the quantities of Natural Gas which Shipper
may then require, up to the quantities of Natural Gas
Transporter is then obligated to deliver to Shipper,
Transporter shall not be liable in damages or
otherwise to Shipper or any other Person or entity for
any such failure to deliver such quantities of Natural
Gas to or for the account of Shipper, except to the
extent the orders or directives were issued as a
result of Transporter's gross negligence, undue
discrimination or willful misconduct.