17. POINT(S) OF RECEIPT AND POINT(S) OF DELIVERY (Continued)
(f) Shipper is entitled to give the notice in
Section 17.2(e) no more often than every four (4)
hours.
17.3 Secondary Point(s) of Receipt and Secondary Point(s) of
Delivery
(a) Any Shipper receiving firm transportation service
under Rate Schedule(s) FT-1 or FT-2 shall be permitted
to nominate service on a secondary basis at all
Point(s) of Receipt and Point(s) of Delivery on
Transporter's Pipeline Facilities in accordance with
the GT&C. Any Shipper receiving firm service under
Rate Schedule EAW shall be permitted to nominate
service on a secondary basis at all physical and/or
virtual Point(s) of Receipt and Point(s) of Delivery
located at or upstream of Transporter's Joliet,
Illinois compressor station. Nominations for the
receipt or delivery of Natural Gas at Secondary
Point(s) of Receipt or Secondary Point(s) of Delivery
shall be permitted only to the extent that:
(1) sufficient capacity exists at such Point(s); and
(2) Transporter's Pipeline Facilities can
operationally accommodate such receipt or delivery.
(b) Any transportation from a Secondary Point of Receipt
and/or to a Secondary Point of Delivery shall be at
applicable maximum rates, unless Transporter shall
agree otherwise. Provided further, that any
transportation from any Secondary Point(s) of Receipt
and/or to any Secondary Point(s) of Delivery outside
of the Contract Path shall be subject to incremental
charges associated with Transporter's applicable Rate
Schedule(s) FT-1 or FT-2 maximum 100 percent load
factor rates from such Secondary Points of Receipt to
such Secondary Points of Delivery unless Transporter
shall agree otherwise.