Guardian Pipeline, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/2002, Docket: RP02-534-000, Status: Effective
Original Sheet No. 167 Original Sheet No. 167 : Superseded
GENERAL TERMS AND CONDITIONS
(Continued)
17. POINT(S) OF RECEIPT AND POINTS(S) OF DELIVERY (Continued)
(4) Upon the receipt of Transporter's
confirmation in Section 17.1(b)(3), the
change(s) in Primary Point(s) of Receipt
and/or Primary Point(s) of Delivery shall
be effective on the date(s) requested by
Shipper.
(5) Upon the effectiveness of the change(s) in
Point(s) of Receipt and/or Point(s) of
Delivery, any such change(s) shall not
have the effect of increasing or
decreasing the contractual MDQ. After
such change(s), any existing nominations
shall be subject to scheduling under
Section 12.
(c) Additions or deletions of Primary Point(s) of
Receipt or Primary Point(s) of Delivery by a
Shipper pursuant to Section 17.1 shall be
permitted only to the extent that sufficient
capacity exists to accommodate such request
without impairing Transporter's ability to meet
its existing obligations and provided further
that such request, if granted, shall not cause
Shipper's reservation charges paid to
Transporter to decrease. Construction of new or
physical expansion of existing Primary Point(s)
of Receipt or Primary Point(s) of Delivery to
Transporter's Pipeline Facilities will only be
made pursuant to the terms of Section 27 of the
GT&C.
17.2 (a) A Shipper, no more often than every thirty (30)
days, desiring to designate or change its
Designated Limited Notice Point(s) of Receipt
may notify Transporter on or before 5:00 p.m.
CCT seven (7) days prior to the first of the
month on which it wants the designation or
change to be effective.