Guardian Pipeline, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2010, Docket: RP10-926-000, Status: Effective
Second Revised Sheet No. 147 Second Revised Sheet No. 147
Superseding: First Revised Sheet No. 147
GENERAL TERMS AND CONDITIONS
(Continued)
11. NOMINATIONS (Continued)
(3) Intra-day 2 Nomination Cycle:
On the Gas Day
--------------
5:00 p.m. CCT Intra-day nomination leaves
control of Shipper.
5:15 p.m. CCT Receipt of intra-day nomination
by Transporter (including from
title transfer tracking service
providers).
5:30 p.m. CCT Transporter provides quick response
for validity of data elements.
8:00 p.m. CCT Receipt of completed
confirmation by Transporter from
upstream and downstream
connected parties.
9:00 p.m. CCT Receipt of Scheduled Quantity
confirmations (including intra-
day nominations and other
scheduling changes) by Shipper
and point operator(s), and
Scheduled Quantity confirmations
from Intra-day 2 Nomination
shall be effective.
Bumping is not allowed during the Intraday 2 Nomination Cycle.
(b) Intra-day nominations may increase or decrease the
existing nomination quantity by any amount, provided
that:
(1) Intra-day nominations, once confirmed and scheduled,
shall have the effect of increasing or decreasing
Shipper's Scheduled Quantity over the remaining
hours in the Day, provided that Transporter shall
not accept an intra-day nomination to decrease the
existing Scheduled Quantity to less than the
Elapsed-prorated-scheduled quantity.