Mobile Bay Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1997, Docket: RP97-155-001, Status: Effective
First Revised Sheet No. 246 First Revised Sheet No. 246 : Effective
Superseding: Superseding Original Sheet No. 246
addition to posting the information on the electronic bulletin
board and contacts a Potential Customer which has not
previously submitted a bid for the subject capacity for the purpose
of obtaining a bid and such Potential Customer submits the "best
bid".
reservation charge when Transporter bills the reservation charge
to the Replacement Customer. The credit will be reflected on the
Releasing Customer's invoice. In the event of default by the
Replacement Customer, the Releasing Customer shall be billed
only for the reservation charge including interest. Any monies
received by Transporter from the Replacement Customer shall be
credited first to the reservation charge and any applicable late
charges. Each Releasing Customer is only responsible for the
breaches of its Replacement Customer.
Releasing Customer that posts capacity for release upon
Transporter's electronic bulletin board, (b) by a Potential or
Prearranged Customer upon its submittal of a bid, and (c) by a
Customer submitting a Capacity Request, as defined in paragraph
(G) of this section, a cost based posting fee not to exceed $25.00.
payment obligations under this tariff, the Releasing Customer
shall have the right to recall the capacity, provided the default is
not cured within fifteen (15) days of the receipt of a notice from
the Releasing Customer to the Replacement Customer that
default has occurred.
General Terms and Conditions who desires capacity may post a request
for capacity (herein called "Capacity Request") on the electronic bulletin
board pursuant to Section 27.7 of the General Terms and Conditions.
Such Capacity Request shall be posted on the electronic bulletin board
for a period no longer than one (1) month.