GENERAL TERMS AND CONDITIONS

(Continued)

 

 

The circumstances under which Transporter may issue an OFO

include but are not limited to:

 

(i) The occurrence of an event of force majeure as defined in

Section 20 of these General Terms and Conditions. An order

pursuant to this provision shall be canceled upon

termination of the inability that caused the force majeure

event.

 

(ii) Normal maintenance of the system including replacement of

pipelines or portion thereof, installation of taps, or any

other similar actions affecting the capacity of any

portions of Transporter's system. An order pursuant to

this provision will contain an estimate of the duration of

such planned maintenance and shall be canceled upon its

completion.

 

(iii) The pressure on the system or portion thereof reaches a

pressure that threatens the physical integrity of the

system. An order pursuant to this provision shall be

canceled when the physical integrity of the system is no

longer threatened.

 

(iv) Maintenance of line pack.

 

(v) Any other event or action which Transporter in its

reasonable judgment believes is necessary to preserve the

integrity of Transporter's physical system or any portion

thereof, the maintenance on a operationally sound basis of

total system deliverability, the quality of gas delivered

and/or the enforcement of any provision of this Tariff.