GENERAL TERMS AND CONDITIONS
(Continued)
gravitometer shall be considered as the specific gravity of the
gas delivered during such period. In the event a continuous
sampler is used, the specific gravity of the composite sample so
taken shall be considered as the specific gravity of the gas
delivered during an applicable period as determined by
Transporter. In the event a spot sample is taken or a
continuous gas sampler is used, the specific gravity of the
composite sample so taken shall be considered as the specific
gravity of the gas delivered during an applicable period as
determined by the Transporter. All specific gravity
determinations made with a chromatograph shall use physical gas
constants for gas compounds as outlined in the 1985 edition of
A.G.A. Report No. 3 (ANSI/API 2530, GPA 8185) on "Orifice
Metering of Natural Gas" with any subsequent amendments or
revisions as may be acceptable to Transporter, and shall meet
generally accepted industry standards and practices. Specific
gravity shall be determined to the nearest one thousandth
(0.001).
delivery point is not determined by any one of the methods
described above, the specific gravity of the gas delivered
during a month shall be assumed to be the same as the weighted
average of the specific gravity of the gas along the same
pipeline segment determined by any of the methods described
above during such period.
any agreement between Transporter and Shipper a new method or
technique is developed with respect to gas measurement, or the
determination of the factors used in such gas measurement, such
new method or technique may be substituted for the method set
forth herein if agreeable to Transporter, and meets generally
accepted industry standards and practices.
for the closing of measurement is five (5) business days after
the business month. For treatment of measurement prior period
adjustments, treat the adjustment by taking it back to the
production month. A meter adjustment becomes a prior period
adjustment after the fifth business day following the business
month. Measurement data corrections should be processed within
six months of the production month with a three month rebuttal
period. This time limitation will not apply in cases of
deliberate omission or misrepresentation or mutual mistake of
fact. Parties’ other statutory or contractual rights shall not
otherwise be diminished by this provision. Any measurement
prior period adjustments will be reported in the original
production month and will be reported with the restated line
item with new total