GENERAL TERMS AND CONDITIONS

(continued)

 

With respect to the processing of requests for decreases during the Evening,

Intraday 1 or Intraday 2 Nomination Cycles, in the absence of agreement to the

contrary, the lesser of the confirmation quantities should be the new confirmed

quantity, but in any event no less than the elapsed-prorated-scheduled quantity.

If there is no response to a Request For Confirmation or an unsolicited

Confirmation Response, the greater of the confirmation quantity or the elapsed-

prorated-scheduled quantity should be the new confirmed quantity.

 

With respect to the preceding three paragraphs, if there is no response to a

request for confirmation or an unsolicited confirmation response, the

Transportation Service Provider should provide the Service Requester with the

following information to explain why the nomination failed as applicable:

(1) the Service Requester's Transportation Service Provider did not conduct the

confirmation;

(2) the Service Requester is told by its Transportation Service Provider that

the upstream confirming party did not conduct the confirmation;

(3) the Service Requester is told by its Transportation Service Provider that

the upstream Service Requester did not have the gas or submit the

nomination;

(4) the Service Requester is told by its Transportation Service Provider that

the downstream confirming party did not conduct the confirmation;

(5) the Service Requester is told by its Transportation Service Provider that

the downstream Service Requester did not have the market or submit the

nomination.

This information should be imparted to the Service Requester on the Scheduled

Quantity document.

 

Transporter shall notify Shipper of the quantities of gas confirmed for receipt

from and delivery to or for the account of Shipper. In the event of an inability

of Transporter to obtain an upstream or downstream confirmation, Transporter may

notify Shipper of such lack of confirmation contact in order that confirmation may

otherwise be obtained.

 

Transporter reserves the right to verify that the quantities of gas, requested by

the Shipper, are flowing as confirmed and scheduled by the Transporter and to

interrupt receipt or deliveries pursuant to an Operational Flow Order under Section

17C.3 to the extent such quantities are not flowing as scheduled.

 

C. Scheduling

The term "Scheduling" herein refers to the allocation of available capacity among

confirmed nominations for each day on Transporter's system, as set forth below.