Florida Gas Transmission Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2006, Docket: RP06-463-000, Status: Effective
Original Sheet No. 219 Original Sheet No. 219 : Effective
GENERAL TERMS AND CONDITIONS
(continued)
partial or entire failure of source of supply, and any other
cause, whether of the kind herein enumerated or otherwise, not
within the control of the party claiming suspension and which
by the exercise of reasonable diligence such party is unable
to prevent or overcome; such term shall likewise include in
those instances where either party is required to obtain
servitudes, rights of way grants, permits or licenses to
enable such party to fulfill its obligations hereunder, the
inability of such party to acquire, or the delays on the part
of such party in acquiring, at reasonable cost and after the
exercise of reasonable diligence, such servitudes, rights of
way grants, permits or licenses; and in those instances where
either party is required to furnish materials and supplies for
the purpose of constructing or maintaining facilities or is
required to secure grants or permissions from any governmental
agency to enable such party to fulfill its obligations
hereunder, the inability of such party to acquire, or the
delays on the part of such party in acquiring, at reasonable
cost and after the exercise of reasonable diligence, such
materials and supplies, permits and permissions (provided that
to the extent such party has contracted with an affiliate to
obtain such materials and supplies, permits, and permissions,
such party shall be entitled to rely on this provision to
excuse such inability or delay only to the extent of an
inability or delay reasonable in comparison to arms-length
transactions with nonaffiliates).
d. It is understood and agreed that the settlement of strikes or
lockouts or other industrial disturbances shall be entirely
within the discretion of the party having the difficulty, and
that the above requirement that any force majeure shall be
remedied with all reasonable dispatch shall not require the
settlement of strikes or lockouts by acceding to the demands
of the opposing party when such course is inadvisable in the
discretion of the party having the difficulty.
e. It is understood and agreed that in the event Transporter has
arranged for third party transportation with a Transporting
Pipeline, and such Transporting Pipeline asserts force
majeure, such event of force majeure on the Transporting
Pipeline system shall constitute force majeure only to the
extent Transporter fails to meet its obligations under its
rate schedules as a result of such force majeure event.