Florida Gas Transmission Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2010, Docket: RP10-21-004, Status: Effective
2nd Sub Sixteenth Revised Sheet No. 13 2nd Sub Sixteenth Revised Sheet No. 13
Superseding: Fifteenth Revised Sheet No. 13
Currently Effective Rates
INTERRUPTIBLE WESTERN DIVISION TRANSPORTATION
Cents per MMBtu
Fuel
GT&C Reimbursement
Rate Rate Sect. 22 Maximum Minimum Charge
Schedule _ Description __ Per MMBtu ACA Rate Rate Percentage 4/
ITS-WD INTERRUPTIBLE TRANSPORTATION
Forwardhaul
Usage 1/ 0.19 ¢ 1/ + 0.19¢ 2/ + 0.19¢ 3/
Backhaul/Exchange
Usage 2/ 0.19 ¢ 2/ + 0.19¢ 2/ + 0.19¢ -
1/ Usage rate shall be 9.31¢/MMBtu plus 0.22¢/MMBtu per 25 miles or any portion thereof in
excess of 100 miles; provided, however, transportation where the quantity is received at an
In-Line Transfer Point from an IPS shipper shall include the longest path mileage within the
zone of the In-Line Transfer Point.
2/ Usage rate shall be 0.88¢/MMBtu plus 0.22¢/MMBtu per 25 miles or any portion thereof in
excess of 100 miles; provided, however, transportation where the quantity is received at an
In-Line Transfer Point from an IPS shipper shall include the longest path mileage within the
zone of the In-Line Transfer Point.
3/ Fuel reimbursement charge shall include any fuel charges by Transporting Pipelines and the
fuel reimbursement charge percentage pursuant to Section 27 of the General Terms and
Conditions is 0.50% per compressor station up to a maximum of 2.78%.
4/ In addition to the fuel reimbursement charges in footnote 3 above, for any Forwardhaul or
Backhaul transportation where the quantity is received at an In-Line Transfer Point from an
IPS shipper, Transporter shall retain a fuel reimbursement charge percentage of 0.50% per
compressor station for all compressor stations within the same zone as the In-Line Transfer
Point up to a maximum of 2.78% for the entire transaction.