RATE SCHEDULE FT

Firm Transportation Service

 

 

3.3 Shipper Reimbursement. In the event that Transporter agrees to install facilities

in order to provide service to Shipper in consideration of Shipper’s agreement to

reimburse Transporter’s cost of installing such facilities, then Shipper shall, in

addition to the charges referenced above, reimburse Transporter for the following:

 

(a) The costs of any facilities installed by Transporter with Shipper’s consent

to receive, measure, transport or deliver Natural Gas for the account of

Shipper;

 

(b) Any and all filing and approval fees required in connection with Shipper’s

Transportation Service Agreement that Transporter is obligated to pay to the

FERC or any other governmental authority having jurisdiction; and

 

(c) An amount reflecting the income tax liability incurred by Transporter as a

result of the receipt of reimbursements pursuant to subsections 3.3 (a), (b)

or (c) of this FT Rate Schedule.

 

Any reimbursement due Transporter by Shipper pursuant to this Section 3.3

shall be due and payable to Transporter within ten days of the date of

Transporter’s invoice(s) for same. Nothing in this Section 3.3 shall be

construed as requiring Transporter to install facilities.

 

4. NOMINATIONS AND SCHEDULING OF RECEIPTS AND DELIVERIES

 

If Shipper desires Transportation of Natural Gas on any day under this rate schedule,

Shipper shall provide a nomination to Transporter in accordance with this Section 4 or the

General Terms and Conditions of this Tariff. Based upon the nomination of Shipper,

Transporter shall schedule receipts and deliveries of Gas in accordance with the General

Terms and Conditions of this Tariff. It is the responsibility of Shipper to adjust its

deliveries and receipts to conform to the General Terms and Conditions of this Tariff.

 

Daily deliveries of Gas by Shipper to Transporter at the Receipt Point(s) hereunder shall

be as nearly equal as possible to daily receipts of Gas by Shipper from Transporter at

the Delivery Point(s) (taking into account the L & U Percentage). Any excess or

deficiency in such receipts and deliveries shall be resolved in accordance with the

General Terms and Conditions of this Tariff.

 

5. OTHER OPERATING CONDITIONS

 

Transporter’s obligations to provide service under this rate schedule is subject to the

following conditions being satisfied:

 

5.1 Shipper shall make all necessary arrangements with other parties at or upstream

of the Receipt Point(s) where Shipper tenders Gas to Transporter for

transportation, and at or downstream of the Delivery Point(s) where Transporter

delivers Gas for Shipper’s account, which arrangement must be compatible with

Transporter’s system operations and Shipper’s service entitlements.

 

5.2 To the extent that any upstream entity involved in handling Shipper’s Gas refuses

or is unable to deliver Gas to Transporter in sufficient quantities and at

sufficient pressures, Transporter shall not be required to continue deliveries

of Gas on behalf of Shipper. To the extent that any downstream entity involved

in handling Shipper’s Gas refuses or is unable to receive Gas from Transporter,

Transporter shall have the right to reduce deliveries of Gas on behalf of Shipper.