TRANSPORTATION GENERAL TERMS AND CONDITIONS
(Continued)
4. SCHEDULING AND CAPACITY ALLOCATION (Continued)
4.3 Adjustments to Confirmation Volumes Received by El Paso in the
Event of Supply Underperformance (Continued)
(iii) Interconnection or Residue Plant Underperformance -
Receipts from interconnecting pipelines and third
party plants shall be monitored by El Paso on a
daily basis where real time data is available. When
actual receipts are less than confirmed volumes and
the shortfall in receipts threatens the integrity of
El Paso's system, El Paso shall notify the
interconnect and plant Operators and request
Operators to increase deliveries or reduce confirmed
volumes prospectively.
In the event interconnect or third party plant
Operators fail to make adjustments, El Paso shall
limit, on a pro rata basis, prospective confirmed
volumes to actual receipts of supply on the day in
question. Higher confirmations shall be allowed
prospectively only when the Operator increases
volumes of gas into El Paso's system.