3. MEASUREMENT EQUIPMENT
3.l Installation and Operation of Measuring Facilities - All
measuring facilities shall be installed, if necessary, owned,
maintained and operated, at or near the Receipt Point(s) and
Delivery Point(s), as mutually agreed to by El Paso and
Shipper. The parties agree that new measurement equipment and
techniques which may be developed from time to time, including
electronic flow measurement equipment and techniques, may be
utilized by either party to measure the quantity of gas
delivered to or by El Paso without additional authorization
from the other party provided such new equipment or technique
is recognized as generally acceptable for the intended purpose
by recognized industry authorities, provides audit data
acceptable by El Paso, and is installed and operated in
accordance with generally accepted industry practices. Unless
otherwise agreed to between the parties, orifice meters shall
be utilized and shall employ flange taps and shall be
installed and operated in accordance with the applicable
American Gas Association reports.
3.2 Installation and Operation of Check Meters - Either party may
install, maintain and operate at its own expense, at or near
the Receipt Point(s) and the Delivery Point(s), check meters
and other necessary equipment by which the quantity of gas
delivered to or by El Paso may be measured, provided that such
equipment is installed so as not to interfere with the
operation of the primary measuring facilities provided for in
Section 3.1 hereof. Unless otherwise agreed to between the
parties, orifice meters shall be utilized and shall employ
flange taps and shall be installed and operated in accordance
with the applicable American Gas Association reports.
3.3 Non-interference - Measuring equipment applying to or
affecting deliveries shall be installed in such manner as to
permit an accurate determination of the quantity of gas
delivered and ready verification of the accuracy of
measurement. The parties shall exercise care in the
installation, maintenance and operation of check measuring or
pressure regulating equipment or gas compressors so as to
prevent any inaccuracy in the determination of the quantity of
gas being measured.