El Paso Natural Gas Company
First Revised Volume No. 1-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/1991, Docket: RP88- 44-022, Status: Effective
Substitute Original Sheet No. 148 Substitute Original Sheet No. 148 : Superseded
RATE SCHEDULE CSI
Contract Storage Interruptible
(Continued)
7. INJECTION PROVISIONS (Continued)
require one (1) compressor unit to run at a 50% load during a
24 hour period (approximately 66 MMcf per day). The actual
deliveries of such gas to El Paso for injection into the
Washington Ranch Storage Facility shall be in accordance with
the terms and conditions of the Service Agreement and/or
applicable Transportation Service Agreement between El Paso
and Shipper. Injection of delivered gas into storage shall be
governed by, and subject to, the terms and conditions of the
executed Contract Storage Service Agreement between El Paso
and Shipper. Nothing herein shall limit El Paso's right to
interrupt storage service hereunder when necessary to test,
alter, modify, enlarge or repair any facility or property
comprising a part of, or appurtenant to, the Washington Ranch
Storage Facility, or otherwise related to the operation
thereof.
7.2 Shipper warrants that it will, at the time of delivery to
El Paso for injection, have good and merchantable title to all
gas so delivered to El Paso free and clear of all liens,
encumbrances and claims whatsoever.
8. WITHDRAWAL PROVISIONS
Withdrawals from the Washington Ranch Storage Facility are
normally limited to the period extending from November 1 of each
calendar year through March 31 of the following calendar year;
however, Shipper may request El Paso to withdraw quantities of
natural gas from storage outside of said period. For any day
during which Shipper desires El Paso to withdraw gas stored for
Shipper's account under this Rate Schedule, Shipper shall advise
El Paso during normal business hours of the quantity of natural
gas, not to exceed Shipper's Maximum Daily Withdrawal Quantity or
the lesser of Shipper's total Maximum Storage Quantity or Shipper's
actual balance in storage which Shipper desires to have withdrawn
from the Washington Ranch Storage Facility. The actual deliveries
of such gas from storage, by El Paso to Shipper and the further
transportation of such gas by El Paso to its ultimate destination,
shall be in accordance with the terms and conditions of the
respective executed Contract Storage Service Agreement and the
applicable Transportation Service Agreement between El Paso and
Shipper.