El Paso Natural Gas Company
Second Revised Volume No. 1A
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2010, Docket: RP10-454-001, Status: Effective
Eighth Revised Sheet No. 405 Eighth Revised Sheet No. 405
Superseding: Seventh Revised Sheet No. 405
FORM OF TRANSPORTATION SERVICE AGREEMENT
APPLICABLE TO FIRM TRANSPORTATION SERVICE UNDER
RATE SCHEDULE FT-1
(Continued)
EXHIBIT A
To The
Transportation Service Agreement
Dated _____________,
Between El Paso Natural Gas Company
and ______________
The following data elements shall be described on this Exhibit A, if
applicable:
Effective Month 1/
Primary Receipt Point (including, among other things, name,
scheduling code, DRN Code(s)) 2/
Primary Delivery Point (including, among other things, name,
scheduling code, DRN Code(s), meter no., and meter DRN
Code(s))
Alternate Receipt Point (including, among other things, name,
scheduling code, DRN Code(s))
Alternate Delivery Point (including, among other things,
name, scheduling code, DRN Code(s), meter no., and meter
DRN Code(s))
Flow Path 3/
Maximum Quantity (dth/d) 4/
Use as appropriate:
Maximum Quantity - Meter (dth/d)5/
-or-
Maximum Quantity - D-Code (dth/d) 5/
Meter Name(s) and CMQ(s) 6/
Delivery Pressure (p.s.i.g.) Not less than 7/
Delivery Pressure (p.s.i.g.) Not greater than 7/
Shipper's Transportation Contract Demand: See Paragraph 11
1/ The calendar Month the specified rights are in effect during the term of
the Agreement.
2/ Necessary pressure to enter the El Paso System and, except as otherwise
noted, not in excess of.
3/ As defined in Section 8.1(e) of the GT&C of El Paso's Tariff.
4/ The "Maximum Quantity" means the daily Maximum Receipt Quantity, Maximum
Delivery Quantity, or Path Quantity, as applicable.
5/ The sum of the Maximum Quantities identified above is equal to Shipper's
Transportation Contract Demand for that Month.
6/ The sum of the CMQs identified above is equal to Shipper's D-Code Maximum
Quantity for that Month.
7/ Unless otherwise specified on this Exhibit A, the delivery pressure(s) for
the point(s) listed above shall be the pressure existing from time to time
at the metering facility; provided, however, El Paso reserves the right to