El Paso Natural Gas Company

Second Revised Volume No. 1A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2010, Docket: RP10-454-001, Status: Effective

Original Sheet No. 327 Original Sheet No. 327

 

TRANSPORTATION GENERAL TERMS AND CONDITIONS

(Continued)

 

16. RESERVATION CHARGE CREDIT (Continued)

 

16.2 Subject to the provisions of Section 16.1, reservation charge

credits shall apply to:

 

(a) Quantities nominated and confirmed to primary delivery points

in Cycle 2, but which Transporter was unable to schedule due

to a capacity shortfall;

 

(b) Quantities scheduled to primary delivery points in Cycle 2

that are subsequently reduced in Cycle 3 due to a capacity

shortfall; and

 

(c) Quantities nominated and confirmed to primary delivery points

in Cycle 3 but which Transporter was unable to schedule due

to a capacity shortfall.

 

16.3 Reservation charge credits shall be calculated as follows:

 

(a) The quantity on which credits are payable shall be calculated

as follows and shall be adjusted for the requirements of

Sections 16.1 and 16.2. The credit shall be payable on the

sum of:

 

(i) 100% of the total for the Month of the Cycle 2 primary

confirmed nominations minus the total for the Month of

the Cycle 2 scheduled quantities as adjusted for

purposes of this computation by Sections 16.1 and 16.2

(a) and (b);

 

(ii) 100% of the total for the Month of the new Cycle 3

primary confirmed nominations for each Day minus the

total for the Month of the Cycle 3 scheduled quantities

as adjusted for purposes of this computation by

Sections 16.1 and 16.2(c).

 

In no event shall the same dth of gas be included more than

once in such calculation.