8. OPERATING PROVISIONS
8.1 FIRM SERVICE (Continued)
(f) (iii) Re-designation of Existing Primary Points (Continued)
(H) Except as provided in Section 9.21(b), re-designations
of Receipt and Delivery Points will result in a
permanent change for every Month of the remaining term
of the TSA. Accordingly, such changes will result in a
corresponding reduction in contract quantity at the
original (vacated) primary points. Transporter will
make the capacity at the vacated points available for
other Shippers to use on a firm and interruptible
basis. The original Shipper may return to the vacated
primary points at a later date only if the capacity is
available to and at those points at that time and the
Shipper submits a re-designation request pursuant to
the procedures of this Section.
(I) If the re-designation of primary points requires the
construction of facilities, then the timing
requirements of this Section 8.1(f)(iii) shall not
apply. If Transporter and Shipper agree that
Transporter shall construct facilities, Shipper must
provide Transporter sufficient notice to obtain the
necessary regulatory and environmental authorizations
to construct and operate the new point under the
Commission's Regulations.