8. OPERATING PROVISIONS
8.1 FIRM SERVICE (Continued)
(e) (ii) Pathing (Continued)
(G) South-to-North Path Rights
1. S/N1 Flow Path rights are assigned to Shippers
with primary SPT receipt points and primary NPT
delivery points. The identified Flow Path for
S/N1 Path rights is between the Cornudas Station
and Wenden Station using the South System, north
on the Havasu crossover to Franconia Junction and
as far west as the Topock area using the North
System.
2. S/N2 Flow Path rights are assigned to Shippers
with primary SPT receipt points and primary NPT
delivery points. The identified Flow Path for
S/N2 Path rights is from the primary receipt
point towards Valve City using the Permian-San
Juan Crossover and from Valve City west towards
the Topock area using the North System.
3. S/N3 Flow Path rights are assigned to Shippers
with primary SPT receipt points and primary NPT
delivery points in the Anadarko area. The
identified Flow Path for S/N3 Path rights is from
the primary receipt point towards Plains and from
Plains north towards the Anadarko area.
(H) Permian-San Juan Crossover Path Rights
1. X/O1 Flow Path rights are assigned to Shippers
with primary SPT receipt points and primary
delivery points along the Permian-San Juan
Crossover. The identified Flow Path for X/O1
Path rights is from the Plains Station to the
Delivery Point along the Permian-San Juan
Crossover.