4. REQUESTS FOR SERVICES
4.7 Capacity Reserved for Future Expansion Projects (Continued)
(e) When an open season is held prior to the expansion project
open season, Transporter shall have the right to state in
the open season posting minimum terms and conditions for
bids that would be acceptable for consideration that are
the same as the minimum terms and conditions anticipated
for the future expansion project open season. In the event
that the subsequent expansion project open season imposes
minimum terms and conditions that are materially different
from the terms and conditions imposed in the previous
capacity open season, Transporter shall hold another open
season for the capacity that uses the same minimum terms
and conditions as were imposed for the expansion project
open season. If the expansion project open season is held
prior to or during the capacity open season, Transporter
shall use the same minimum terms and conditions as used for
the expansion project open season.
(f) Any capacity reserved under this Section 4.7 shall be made
available for transportation service pursuant to the GT&C
on a limited-term basis up to the in-service date of the
expansion project(s). For such limited-term TSAs,
Transporter reserves the right to limit any term extension
rights provided in the TSA and pursuant to Section 4.14
commensurate with the proposed in-service date of the
expansion project. Transporter will indicate in any open
season posting of the capacity any limitations on term
extension rights that will apply to such limited-term
transportation service.
(g) Any capacity reserved for a project that does not go
forward for any reason shall be reposted as generally
available capacity within 30 Days of the date that the
project terminates, with the exception of capacity
committed to in contracts entered into on an interim
limited-term basis until the in-service date of any
expansion facilities during the period the capacity was
reserved.