TRANSPORTATION GENERAL TERMS AND CONDITIONS (Continued)

 

4. SCHEDULING AND CAPACITY ALLOCATION (Continued)

 

4.1 Scheduling of Receipts and Deliveries (Continued)

 

(a) (Continued)

Flow Day - Shippers shall cause the Operators to tender the

scheduled quantities of natural gas to El Paso at Receipt

Points, plus volumes to be retained by El Paso for fuel and

shrinkage as provided for in the applicable transportation

rate schedule, and El Paso shall deliver the scheduled

quantities of natural gas, for Shippers' accounts, at

Delivery Points.

 

Intra-day Scheduling - Shippers may each day submit one

intra-day scheduling request per agreement up to four hours

prior to the beginning of gas flow. Intra-day scheduling

requests may be used to request increases or decreases in

total flow, changes to receipt points, or changes to

delivery points of scheduled gas. El Paso will schedule

such requests at least once per day using the allocation

priorities established in Section 4.2.

 

Where additional capacity exists, Shippers may submit an

intra-day request for transportation of additional

quantities of gas. Shippers shall cause the Operator to

make corresponding confirmations of supply or downstream

capacity. Such scheduling shall apply only to the

additional capacity and shall not cause any change in the

prior sequencing of deliveries. El Paso shall communicate

electronically or via facsimile the final scheduling of

additional quantities of gas to Shippers and Operators prior

to the end of flow day.

 

In addition, Shippers may reduce previously scheduled

quantities of gas. Shippers shall cause the Operator to make

corresponding confirmations of reduced supply or downstream

capacity. El Paso shall communicate electronically or via

facsimile the reduction of scheduled quantities to Shippers

and Operators prior to the end of flow day.