El Paso Natural Gas Company

Second Revised Volume No. 1A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/2009, Docket: RP08-426-000, Status: Effective

Third Revised Sheet No. 150B Third Revised Sheet No. 150B

Superseding: Second Rev First Revised Sheet No. 150B

 

RATE SCHEDULE OPAS

Operator Point Aggregation Service

(Continued)

 

2. APPLICABILITY AND CHARACTER OF SERVICE (Continued)

 

2.7 To the extent required by Transporter for informational purposes, the

DP Operator must designate the individual meter(s) at which alternate

firm or any interruptible transportation service will be taken.

 

2.8 DP Operator shall have the option of electing one alternative set of

MDOs/MHOs for meters in a D-Code. The alternative set must be

mutually agreed to by Transporter and DP Operator when the OPASA is

executed or modified. The alternative set would apply depending on

the level of alternate firm or interruptible transportation that the

DP Operator confirms at the D-Code. DP Operator shall notify

Transporter prior to the Timely Nomination Cycle 1 for the Gas Day

that the alternative set of MDOs/MHOs will be used.

 

2.9 Should the DP Operator take gas on an hourly or daily basis at any

individual delivery meter that exceeds the MHO or the MDO,

respectively, for that meter, DP Operator will pay an MDO/MHO

violation penalty pursuant to Section 4 of this rate schedule.

 

3. RATE

 

3.1 Rates. DP Operators shall not be charged any rates by Transporter

for service under this Rate Schedule; however, the DP Operator will

be subject to the MHO/MDO violation penalties described in Section 4

of this rate schedule.

 

3.2 Surcharges: No surcharges are applicable to service under this Rate

Schedule.

 

3.3 Fuel Charges: Fuel charges are not applicable to service under this

Rate Schedule.

 

4. MHO or MDO VIOLATION PENALTIES

 

4.1 On any Day, any Flowing Gas quantity at a delivery meter which

exceeds the MDO for that meter is an MDO violation. Subject to

Section 4.6 of this Rate Schedule, DP Operator shall pay an amount

obtained by multiplying the quantity taken in excess of the MDO by

the penalty rate listed on the applicable Statement of Rates for a

Critical or non-Critical Condition as appropriate.