RATE SCHEDULE ISS
Interruptible Storage Service
(Continued)
2. APPLICABILITY AND CHARACTER OF SERVICE (Continued)
2.4 On any Gas Day, any TSA may be used to transport gas to and from
storage.
3. CONDITIONS OF SERVICE
3.1 Interruptible storage service must be nominated and confirmed to the
ISS TSA in accordance with the provisions of Section 6 of the GT&C.
3.2 Upon issuance of a notice of Critical Condition that affects
Transporter's use of pipeline capacity for higher priority services
or operational requirements, Transporter may require Shipper to 1)
suspend its injections into storage, 2) suspend its withdrawals from
storage, or 3) withdraw its storage inventory on an expedited basis.
Notification of the required activity shall be made pursuant to the
notification procedures of Section 6.1(a)(xii) of the GT&C.
(a) Such notification shall only be made when the required Shipper
action is necessary to protect the operational integrity and
flexibility of Transporter's pipeline system or to allow
Transporter to fulfill higher priority commitments.
(b) Upon notification by Transporter of required expedited storage
withdrawals, Shipper will be required to submit a nomination
pursuant to Section 6 of the GT&C in the next available
nomination cycle to withdraw, no later than the next Gas Day,
the greater of ten percent of Shipper's existing interruptible
inventory or 5,000 Dth. Withdrawals at the same rate on
subsequent Gas Days may also be required by Transporter.