GENERAL TERMS AND CONDITIONS (Continued)
15.4 Allocation of Limited Capacity
(a) Curtailment: If, on any Day, Transporter determines that the
capacity of its system, or any portion thereof including the
point(s) at which gas is tendered for transportation is
insufficient to serve all Shippers that are scheduled to receive
service on such Day, capacity that requires allocation shall be
allocated in a manner that results in curtailment of capacity, to
zero if necessary, in reverse of the order listed in Section
15.3(a) above if curtailing at a Receipt or Delivery Point or in
Section 15.3(b) above if curtailing at a pipeline location such as
a compressor station; provided, however, if capacity must be
allocated within the services included in Sections 15.3(a)(i)
through 15.3(a)(iii) or in Sections 15.3(b)(i) through
15.3(b)(iii), such capacity will be curtailed pro rata based on
Scheduled Quantities. If interruptible transportation must be
allocated, such transportation will be curtailed according to the
price being paid, with lower priced transportation being curtailed
before higher priced transportation. Provided that, for the
purpose of the foregoing sentence, any Shipper paying above the
maximum IT or IT-L rate shall be deemed to be paying the maximum
applicable rate. If PAL service must be allocated, such service
shall be curtailed according to the net present value of each
transaction, with transactions yielding a lower net present value
being curtailed before those transactions yielding a higher net
present value.
(b) [Reserved for Future Use]