5.8 Allocation of Firm Capacity (continued)

 

(a) Existing Capacity (continued)

 

(4) For any open season conducted pursuant to this Section

5.8(a) for service with a term of less than ninety

(90) Days, the open season will be conducted for a

duration of one (1) Business Day. For an open season

under this Section 5.8(a) for service with a term

equal to or greater than ninety (90) Days, the open

season will be conducted for a duration of (i) five

(5) Business Days from the posting of the notice of

request for service for the capacity or (ii) fifteen

(15) Business Days from the date the capacity in

question was first posted as being available for

contracting, whichever is the later calendar date. In

no event shall the open season be held for a period

greater than one (1) calendar month.

 

(5) Bidders who desire service to be provided in whole or

in part by the capacity posted pursuant to this

Section 5.8(a) must submit bids for such capacity

online via the LINK® System.

 

(6) To be a valid bid, a bid must comply with the bid

requirements set forth in Section 5.8(a)(5). In

addition, the bidder must provide all information and

data required by Sections 5.2 and 6 of these General

Terms and Conditions. Transporter reserves the right

to reject any bid (i) that contains a rate that is

less than maximum rate, (ii) that may adversely affect

the operational integrity of Transporter's system,

(iii) that does not satisfy all the terms of the

applicable posting, (iv) for which the requesting

Shipper does not demonstrate creditworthiness pursuant

to Section 6 of the General Terms and Conditions,

and/or (v) that contains terms and conditions other

than those provided for in Transporter's FERC Gas

Tariff. If Transporter rejects any request for

available capacity posted pursuant to this Section

5.8, Transporter will notify the bidder via e-mail of

its reason(s) for such rejection.