5. SCHEDULING AND CURTAILMENT
Transporter shall schedule interruptible transportation according to the
IT-L rate paid by Shippers each Month, scheduling requests for IT-L
service at higher rates ahead of requests for IT-L service at lower
rates. The foregoing notwithstanding, if an IT-L Shipper was flowing
gas under its IT-L Agreement during the previous Month, such Shipper
will be notified prior to the start of the Month of delivery if its
current IT-L nomination can not be scheduled due to price, and given an
opportunity to offer a price that will enable its IT-L nomination to be
scheduled. IT-L Shippers paying the same rate shall be scheduled pro
rata based on Scheduled Quantities.
6. FUEL AND LOSSES
Shipper shall furnish the quantity of gas required for fuel and losses
associated with rendering transportation service pursuant to this Rate
Schedule. NAESB WGQ Standard 1.3.16 states: Where fuel reimbursement
is in kind, the standard fuel calculation mechanism, as this is related
to the nomination process, should be (1-fuel%/100) multiplied by receipt
quantity = delivery quantity. In accordance with this NAESB WGQ
Standard, the quantity of gas retained by Transporter for fuel and
losses shall equal the quantity of gas tendered at the receipt point
multiplied by the applicable fuel and loss retention percentage shown on
the effective Notice of Rates and Other Tariff Rate Changes of
Transporter's effective FERC Gas Tariff. Once each calendar year,
Transporter shall have the right to file with the Commission to change
the quantity of gas required for fuel and losses for the facilities
designated as an Incremental Lateral.
7. MONTHLY BILL
The Monthly Bill for service shall equal
(a) The applicable IT-L Rate multiplied by the Dekatherms of natural
gas transported and delivered by Transporter for Shipper during
the Month pursuant to this Rate Schedule; and
(b) If applicable, any other charges pursuant to Section 4 of this
Rate Schedule.
8. WAIVER
Transporter may waive any rights hereunder or any obligations of Shipper
hereunder on a basis that is not unduly discriminatory; provided that no
waiver shall operate or be construed as a waiver of other or future
rights or obligations, whether of a like or different character.
9. GENERAL TERMS AND CONDITIONS
9.1 Shipper shall provide Transporter with such information as is
needed to meet the requirements placed on Transporter by
regulation, rule, and/or order by any duly authorized agency.
Furthermore, any terms or conditions not specified in this Rate
Schedule shall be determined consistent with the General Terms and
Conditions of Transporter's FERC Gas Tariff, which are
incorporated into this Rate Schedule.
9.2 In the event of a conflict between the provisions of this Rate
Schedule and Transporter's General Terms and Conditions, the
provisions of Transporter's General Terms and Conditions shall
govern.