IT-L RATE SCHEDULE

INTERRUPTIBLE LATERAL TRANSPORTATION SERVICE

 

 

3. DELIVERIES AND RECEIPTS (continued)

 

3.2 Delivery Points: All delivery points on the applicable

Incremental Lateral shall be available as delivery points for gas

transported under this Rate Schedule. Transporter shall not be

required under any circumstances to deliver gas at any Delivery

Point where (1) the total quantity of gas scheduled for delivery

on any Day is less than that required for the accurate measurement

of quantities to be delivered or (2) the total quantity of gas

scheduled for delivery at such point is less than that required to

operate compression facilities necessary to deliver gas to such

point.

 

4. RATES AND CHARGES

 

4.1 Transportation Rates: The Transportation Rate is the maximum IT-L

rate shown on the effective Notice of Rates and Other Tariff Rate

Changes, unless otherwise mutually agreed; provided, however,

Transporter has the right at any time and from time to time to

adjust the rate applicable to any transportation service upon

notice to Shipper to any level not less than the minimum nor more

than the maximum rates established for this Rate Schedule and set

forth on the effective Notice of Rates and Other Tariff Rate

Changes. By mutual agreement between Transporter and Shipper,

discounts may be limited consistent with the provisions of Section

41 of the General Terms and Conditions of Transporter's FERC Gas

Tariff.

 

In the event Transporter and Shipper agree to establish a

discounted rate pursuant to Section 41 of the General Terms and

Conditions of Transporter's FERC Gas Tariff, said rate will be set

forth in the Discount Confirmation sent to Shipper. Transporter

shall file with the Commission the required reports of any

adjustment below the maximum rate(s) for service under this Rate

Schedule.

 

4.2 New Facilities: In addition to the charges pursuant to Section

4.1 of this Rate Schedule, Transporter shall charge Shipper an

amount to reimburse 100% of the cost (including a gross up for the

income tax effects of reimbursement) of facilities constructed at

Shipper's request in order to provide transportation service under

this Rate Schedule. Further, Transporter shall charge Shipper an

amount to reimburse 100% of the cost (including a gross-up for the

income tax effects of reimbursement) of all electronic custody

transfer equipment, metering facilities, gravitometers,

calorimeters, flow controllers and other measurement or metering

facilities.