East Tennessee Natural Gas, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/02/2010, Docket: RP10-946-000, Status: Effective
Second Revised Sheet No. 124A Second Revised Sheet No. 124A
Superseding: First Revised Sheet No. 124A
RATE SCHEDULE FT-GS
FIRM TRANSPORTATION SERVICE
4. RATES AND CHARGES
4.1 Applicable Rates: The applicable rate for service under the FT-GS
Rate Schedule is shown on the effective Notice of Rates and Other
Tariff Rate Changes. Where applicable, such rate is subject to
adjustment pursuant to Sections 25 and 34 of the General Terms and
Conditions of Transporter's FERC Gas Tariff. By mutual agreement
between Transporter and Shipper, discounts may be limited
consistent with the provisions of Section 41 of the General Terms
and Conditions of Transporter's FERC Gas Tariff.
4.2 New Facilities: In addition to the charges pursuant to Section 4.1
of this Rate Schedule, Transporter shall charge Shipper an amount
to reimburse 100% of the cost (including a gross-up for the income
tax effects of reimbursement) of facilities constructed at the
Shipper's request in order to provide transportation service under
this Rate Schedule. Further, Transporter shall charge Shipper an
amount to reimburse 100% of the cost (including a gross-up for the
income tax effects of reimbursement) of all electronic custody
transfer equipment, metering facilities, gravitometers,
calorimeters, flow controllers or other measuring or metering
facilities.