East Tennessee Natural Gas, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/02/2010, Docket: RP10-946-000, Status: Effective
Second Revised Sheet No. 116 Second Revised Sheet No. 116
Superseding: First Revised Sheet No. 116
FT-L RATE SCHEDULE
FIRM LATERAL TRANSPORTATION SERVICE
5. FUEL AND LOSSES
Shipper shall furnish the quantity of gas required for fuel and losses
associated with rendering transportation service pursuant to this Rate
Schedule. NAESB WGQ Standard 1.3.16 states: Where fuel reimbursement
is in kind, the standard fuel calculation mechanism, as this is related
to the nomination process, should be (1-fuel%/100) multiplied by receipt
quantity = delivery quantity. In accordance with this NAESB WGQ
Standard, the quantity of gas retained by Transporter for fuel and
losses shall equal the quantity of gas tendered at the receipt point
multiplied by the applicable fuel and loss retention percentage shown on
the effective Notice of Rates and Other Tariff Rate Changes of
Transporter's effective FERC Gas Tariff. Once each calendar year,
Transporter shall have the right to file with the Commission to change
the quantity of gas required for fuel and losses for the facilities
designated as an Incremental Lateral.
6. MONTHLY BILL
The Monthly Bill for service shall be equal to:
(a) Reservation Charge: A reservation rate determined under Section 4
above multiplied by the Maximum Daily Transportation Quantity as
specified in the FT-L Agreement; and,
(b) Commodity Charge: The applicable Commodity Rate(s) under Section
4 above multiplied by the Dekatherms of natural gas transported
and delivered during the Month pursuant to this Rate Schedule; and
(c) If applicable, any other charges pursuant to Section 4 of the Rate
Schedule.