GENERAL TERMS AND CONDITIONS

Section 20

 

 

20. CONSTRUCTION OF RECEIPT AND DELIVERY FACILITIES

 

20.1 For the purposes of this Section, "Requested Facilities" shall

mean Taps, M&R Equipment or other points of interconnection.

Requested Facilities shall not include a major expansion of

transmission facilities or laterals. "Tap" shall mean a delivery

tap and/or a point of interconnection where Gulf Crossing receives

Gas into its system including but not be limited to, flanges and

block valves and sufficient pipeline from Gulf Crossing's existing

transmission facilities to the edge of its right-of-way. "M&R

Equipment" shall include miscellaneous connecting pipeline to the

tap, meters, compression, flow and pressure regulators,

filters/separators, Gas heaters, flanges, check valves, electronic

Gas measurement, communication equipment and Gas conditioning and

odorization equipment other than equipment included in the Tap.

"Construction" shall mean the construction, modification,

rearrangement, reactivation, or installation by Gulf Crossing, a

Requesting Customer or their designee as defined below, to perform

construction of any Requested Facilities necessary for Gulf

Crossing to receive and deliver, or measure any Gas received or

delivered to, from, or on behalf of any Customer.

 

20.2 A party or its agent shall submit a request to Gulf Crossing to

construct Requested Facilities in conjunction with a request

("Requesting Customer") for either new transportation service or

service pursuant to an existing transportation service agreement.

Gulf Crossing will begin evaluation of such requests within

fifteen (15) Days of receipt and shall complete the evaluation

process and respond to the requesting Customer no later than 30

Days after the request is received. Gulf Crossing will receive

and process all such requests for Construction of Requested

Facilities in a manner that is not unduly discriminatory.