corrected flow and the total measurement adjustment for the Month
is greater than 500 Dth, then any previous recordings of such
equipment shall be corrected to zero error for any period that is
known definitely or agreed upon. Any error determined to be
greater than $50,000 will require correction to zero error for
any period where the error existed (and which is either known
definitely or agreed to by both parties). In the case where the
period is not known or agreed upon, such correction shall be for
a period equal to one-half of the time elapsed since the date of
the last test.
4.16 In the event any measuring equipment is out of service or is
found registering inaccurately and the error is not determinable
by test or by previous recordings, receipts or deliveries through
such equipment shall be estimated and agreed to by the Parties
upon the first of the following methods which is feasible: (a) By
using the registration of any check measurement or meters, if
installed and accurately registering. (b) By correcting the error
if the percentage of error is ascertainable by calibration,
special test, or mathematical calculation. (c) By estimating the
quantity based on receipts and/or deliveries during preceding
periods under similar conditions when the measuring equipment was
registering accurately.
4.17 Customer and Gulf Crossing shall preserve for a period of at
least 5 years, or for such longer period as may be required by
appropriate authority, all test data and other similar records as
defined by API 21.1, including any subsequent amendments or
revisions which meet generally accepted industry standards and
practices and are acceptable to Gulf Crossing and Customer.