Gulf Crossing Pipeline Company LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/20/2008, Docket: RP09-61-000, Status: Effective
Original Sheet No. 452 Original Sheet No. 452
GENERAL TERMS AND CONDITIONS
Section 4
(Continued)
any installing, reading, cleaning, changing, repairing,
inspecting, testing, calibrating, or adjusting done in connection
with the other's measuring equipment; provided, however, failure
of either Gulf Crossing or Customer to witness such an operation
shall not affect the validity of such operation in any way. The
records from such measuring equipment shall remain the property
of their owner, but upon request, each will submit within 10 Days
to the other its records, together with calculations there from,
for inspection, subject to return within 30 Days after receipt
thereof. Unless otherwise agreed, the measurement equipment of
Customer shall be for check purposes only and, except as
expressly provided in the applicable agreement or as needed
through Section 4.15 of this Tariff, shall not be used in the
measurement of Gas for purposes of the Agreement.
4.8 Orifice meters shall be installed and Gas volumes computed in
accordance with the standards prescribed in AGA Report No. 3
"Orifice Metering of Natural Gas", including any subsequent
amendments or revisions which meet generally accepted industry
standards and practices and are acceptable to Gulf Crossing and
Customer.
4.9 Ultrasonic meters shall be installed and Gas volumes computed in
accordance with the standards prescribed in AGA Report No. 9
"Measurement of Gas by Multipath Ultrasonic Meters", including
any subsequent amendments or revisions which meet generally
accepted industry standards and practices and are acceptable to
Gulf Crossing and Customer
4.10 Positive displacement meters shall be installed and Gas volumes
computed in accordance with generally accepted industry practices
as prescribed in ANSI B 109, including any subsequent amendments
or revisions which meet generally accepted industry standards and
practices and are acceptable to Gulf Crossing and Customer.
4.11 Electronic flow computers can be used for direct computation of
Gas flows for custody transfer.