4. PRIORITY OF SERVICE

 

Priority of service shall be determined in accordance with Sections 12

and 18 of the General Terms and Conditions.

 

 

5. RATE

 

Unless otherwise agreed by Gulf Crossing and Customer, Customer shall

pay Gulf Crossing under this FTS Rate Schedule (i) a daily reservation

charge based on Customer's MDQ and (ii) a usage charge for each unit of

Gas delivered. Customer shall also pay Gulf Crossing such other

charges as set forth in this FTS Rate Schedule and the General Terms

and Conditions. The maximum applicable rates per Dekatherm under this

rate schedule are set forth on Sheet No. 20.

 

(a) Unless otherwise agreed upon by Gulf Crossing and Customer as

part of a negotiated rate agreement, the maximum reservation

charge shall be the maximum daily reservation rate multiplied by

Customer's MDQ and multiplied by the number of Days in the

billing month. Where Customer transports Gas on any of Gulf

Crossing's transportation facilities, the maximum usage charge

shall be the maximum unit usage rate multiplied by the quantity

of Gas actually delivered by Gulf Crossing under the FTS service

agreement during the billing month unless otherwise agreed upon

by Gulf Crossing and Customer. Customer shall also pay Gulf

Crossing all other applicable charges as set forth on Sheet No.

20.

 

(b) Gulf Crossing shall retain an in-kind Fuel and Company-Used Gas

allowance at all receipt points as set forth on Sheet No. 20.

 

Gulf Crossing may from time to time determine receipt and

delivery point combinations or paths on its system where fuel

will not be used or charged for a particular transaction ("Zero

Fuel Transactions"). Zero Fuel Transactions will be determined

by a review of projected system flows and the indication that on

an aggregate basis no incremental fuel will be required to

facilitate those transactions. Gulf Crossing will file with the

Commission any Zero Fuel Transactions which Gulf Crossing

proposes to exempt from fuel charges and will demonstrate that

 

__________________________________