Destin Pipeline Company, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2000, Docket: RP00-268-000, Status: Effective
First Revised Sheet No. 134 First Revised Sheet No. 134 : Effective
Superseding: Original Sheet No. 134
GENERAL TERMS AND CONDITIONS
(Continued)
27. CONSTRUCTION OF FACILITIES
In order for COMPANY to receive, measure, transport, and/or
deliver the gas to be transported under one of its Rate
Schedules, it may become necessary for COMPANY to install
facilities or to modify existing facilities at or near a
Receipt Point or Delivery Point. Should SHIPPER request the
installation or modification of said facilities and agree to
reimburse COMPANY for the cost thereof, and should COMPANY
agree to install said facilities or to modify its existing
facilities pursuant to SHIPPER's request, it is agreed that
COMPANY will construct and install, or cause to be
constructed and installed, said facilities, or will modify,
or cause to be modified, its existing facilities, and will
own and operate such facilities and all related appurtenant
facilities. In the event SHIPPER does not agree to pay the
costs of installing or modifying said facilities, COMPANY
may agree to construct or modify such facilities so long as
such facilities are constructed or modified on a
nondiscriminatory basis for similarly situated SHIPPERS.
Whether said facilities will provide a benefit to all
SHIPPERS using COMPANY's pipeline system such that it is
appropriate to include the cost of said facilities in
COMPANY's general system rates will be determined in the
rate proceeding in which COMPANY proposes to include such
costs in its general system rates. It is understood and
agreed that title to and ownership of said facilities shall
remain in COMPANY, and COMPANY shall operate such facilities
as part of its pipeline system.