RATE SCHEDULE FT-2
Firm Transportation Service
(Continued)
Section 3(c) (continued)
(i) ACA charge: An Annual Charge Adjustment charge as prescribed
by Section 23 of the General Terms and Conditions of
COMPANY's FERC Gas Tariff and set forth on currently
effective Sheet No. 6, as said charge may be changed from
time to time.
(ii) Facilities: All costs, including reasonable overheads,
actually incurred by COMPANY in the construction and
installation, modification, and/or acquisition of facilities
for the receipt, measurement, or transportation of gas for
SHIPPER's account which SHIPPER requests and COMPANY, in its
reasonable discretion, agrees to construct, install, modify,
and/or acquire including acquisition of any interests in real
estate and permits associated with the facilities. Title and
ownership of such facilities, however, shall remain in
COMPANY. SHIPPER shall pay COMPANY for such costs within ten
(10) days of receipt of COMPANY's invoice detailing the
amount of such costs.
(iii) Fuel retained: A percentage of the quantity of gas
delivered by SHIPPER for transportation and accepted by
COMPANY at the Receipt Point(s) as gas which shall be deemed
to have been used for compressor fuel and gas otherwise used,
lost, or unaccounted for in COMPANY's operations. The
percentage of the quantity of gas retained by COMPANY for
such purposes shall be set forth on the currently effective
Sheet No. 6 as determined pursuant to the provisions of
Section 24 of the General Terms and Conditions of COMPANY's
FERC Gas Tariff.