Destin Pipeline Company, L.L.C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/18/2008, Docket: RP09-84-000, Status: Effective

Second Revised Sheet No. 21 Second Revised Sheet No. 21

Superseding: Sub First Revised Sheet No. 21

 

RATE SCHEDULE FT-2

Firm Transportation Service

(Continued)

 

 

3. RATES AND CHARGES

 

(a) For transportation services under each Transportation Service

Agreement, SHIPPER shall pay COMPANY the sum of the following for

transportation services rendered for SHIPPER each month under this

Rate Schedule:

 

(i) Reservation Charge: (A) If the sum of the quantity of gas

allocated to SHIPPER's FT-2 transportation Service

Agreement, including scheduled overrun quantities, at the

Receipt Point(s) in the previous three months, including

the production month being billed, equals or exceeds 70% of

the TD specified in the FT-2 transportation Service

Agreement for the same three months multiplied by the

average Shipper Specific Heating Value for the same three

months and multiplied by the number of days in the months,

based on the best available information at the time of

billing, then SHIPPER shall pay to COMPANY the Daily

Reservation Rate set forth on currently effective Sheet No.

6 multiplied by the quantities of gas (in Mcf) received for

SHIPPER's account for the month up to the sum of SHIPPER's

TD in effect on each day during the month multiplied by the

average Shipper Specific Heating Value for the month; or

(B) If the sum of the quantity of gas allocated to

SHIPPER's FT-2 transportation Service Agreement, including

scheduled overrun quantities, at the Receipt Point(s) in

the previous three months, including the production month

being billed, is less than 70% of the TD specified in the

FT-2 transportation Service Agreement for the same three

months multiplied by the average Shipper Specific Heating

Value for the same three months and multiplied by the

number of