Destin Pipeline Company, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/18/2008, Docket: RP09-84-000, Status: Effective
Second Revised Sheet No. 21 Second Revised Sheet No. 21
Superseding: Sub First Revised Sheet No. 21
RATE SCHEDULE FT-2
Firm Transportation Service
(Continued)
3. RATES AND CHARGES
(a) For transportation services under each Transportation Service
Agreement, SHIPPER shall pay COMPANY the sum of the following for
transportation services rendered for SHIPPER each month under this
Rate Schedule:
(i) Reservation Charge: (A) If the sum of the quantity of gas
allocated to SHIPPER's FT-2 transportation Service
Agreement, including scheduled overrun quantities, at the
Receipt Point(s) in the previous three months, including
the production month being billed, equals or exceeds 70% of
the TD specified in the FT-2 transportation Service
Agreement for the same three months multiplied by the
average Shipper Specific Heating Value for the same three
months and multiplied by the number of days in the months,
based on the best available information at the time of
billing, then SHIPPER shall pay to COMPANY the Daily
Reservation Rate set forth on currently effective Sheet No.
6 multiplied by the quantities of gas (in Mcf) received for
SHIPPER's account for the month up to the sum of SHIPPER's
TD in effect on each day during the month multiplied by the
average Shipper Specific Heating Value for the month; or
(B) If the sum of the quantity of gas allocated to
SHIPPER's FT-2 transportation Service Agreement, including
scheduled overrun quantities, at the Receipt Point(s) in
the previous three months, including the production month
being billed, is less than 70% of the TD specified in the
FT-2 transportation Service Agreement for the same three
months multiplied by the average Shipper Specific Heating
Value for the same three months and multiplied by the
number of