20. REQUESTS FOR ADDITIONAL FACILITIES/EXPANDED CAPACITY
20.1 Shipper may request, by use of the Service Request Form,
the addition of facilities to (or connecting to), or
expansion of, Transporter's MP Facility or Transporter's DI
Facility to allow the requesting Shipper to deliver/receive
specified gas quantities under an existing or new
Transportation Service Agreement.
20.2 Transporter shall determine the following information in
response to the above request:
(a) the estimated cost of constructing and installing
the requested additional facilities or modifying
existing facilities ("New Facilities Cost") and an
estimated time to accomplish such; and,
(b) assess the impact of the requested additional
facilities or modified existing facilities on
Transporter's ability to operate its system and
continue to provide service pursuant to then
existing Transportation Service Agreements.
20.3 If Transporter's assessment of the impact to its system is
not negative, then based on the New Facilities Cost, if the
requesting Shipper continues to desire to have the
additional facilities added to Transporter's MP Facility or
Transporter's DI Facility or existing facilities modified,
the requesting Shipper and Transporter shall then execute
the documents required to implement the requested service
- new or amended Transportation Service Agreement, amended
Exhibit "A", etc.
20.4 The provisions of this Section 20 shall not apply to the
expansion of Transporter's MP Facility or Transporter's DI
Facility which would require Transporter to obtain
additional authority from the Commission.
20.5 Transporter shall submit an invoice to the requesting
Shipper in the amount of the estimated New Facilities Cost.
Shipper shall make payment to Transporter pursuant to the
provisions of Section 14.2 of these General Terms and
Conditions.
20.6 Transporter shall commence to construct and install the
requested additional facilities or modify existing
facilities upon receipt of the payment pursuant to Section
20.5.