(b) Intra-day Nominations: An intra-day nomination is a

nomination submitted after the nomination deadline

whose effective time is no earlier than the

beginning of the gas day and runs through the end of

that gas day. Intra-day nominations can be used to

request increases or decreases in total flow,

changes to Receipt Point(s), or changes to Delivery

Point(s) of scheduled gas. Intra-day nominations

may be used to nominate new supply or market.

Intra-day nominations do not roll over (i.e., intra-

day nominations span one day only). Intra-day

nominations do not replace the remainder of standing

nomination. There is no need to re-nominate if

intra-day nomination modifies existing nomination.

 

For services that provide for intraday nominations

and scheduling, there is no limitation as to the

number of intraday nominations (line items as per

GISB Standard 1.2.1) which a Shipper may submit at

any one standard nomination cycle or in total across

all standard nomination cycles. Transporter may

(for an interim period expiring on April 1, 1999)

limit Shippers to one transmittal of nominations per

standard intraday nomination cycle, (excluding

corrections of errors identified in the Quick

Response).

 

(c) Transporter shall support the following standard

nomination cycles:

 

(i) The Timely Nomination cycle: 11:30 a.m. for

nominations leaving control of the nominating

party; 11:45 a.m. for receipt of nominations

by Transporter; noon for quick response; 3:30

p.m. for receipt of completed confirmations by

Transporter from upstream and downstream

connected parties; 4:30 p.m. for receipt of

scheduled quantities by Shipper and point

operator (CCT on the day prior to flow).

 

(ii) The Evening Nomination Cycle: 6:00 p.m. for

nominations leaving control of the nominating

party; 6:15 p.m. for receipt of nominations by

the Transporter; 6:30 p.m. to send Quick

Response; 9:00 p.m. for receipt of completed

confirmations by Transporter from upstream and

downstream connected parties; 10:00 p.m. for

Transporter to provide scheduled quantities to

affected Shippers and point operators, an to

provide scheduled quantities to bumped parties

(notice to bumped parties), (CCT on the day