Dauphin Island Gathering Partners
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2010, Docket: RP10-467-001, Status: Effective
Substitute Original Sheet No. 244 Substitute Original Sheet No. 244
(d) Construction, modifications (including but not limited to
recoating), repair, burials, removal or replacements of
pipeline (including but not limited to Storm-related damage
caused by dragging of shipping anchors and damage to third
parties caused by Storm-related damage to Transporter),
receipt points, delivery points, compressors, buildings,
fences, debris (including but not limited to sunken ships
and platforms), equipment (including but not limited to
removal of Transporter's equipment on offshore platforms
owned by third parties), and other property;
(e) Construction, modifications, repairs and replacements of
pipeline shore approaches, levee crossings and other
water/land interfaces (including but not limited to the
removal of restrictions or obstructions);
(f) the term "Eligible Costs" shall in all cases include only
actual costs incurred to repair damage and/or recover
system operations related to a Storm.
22.3 Effective Date and Filing of Storm Surcharge
(a) The effective Storm Surcharge shall be shown on the
applicable rate sheet of this Tariff. The effective date
of each Storm Surcharge shall be April 1 of each year.
(b) Subsequent to the initial filing implementing Transporter's
Storm Surcharge, Transporter shall file with the Commission
by March 1 the proposed revised Storm Surcharge with
supporting documentation. With each such filing,
Transporter shall include a detailed written description of
all Eligible Costs in its filing (except for any
expenditures carried forward from a prior filing), with an
explanation of how each such expenditure qualifies for
inclusion in the Storm Surcharge. The filing shall also
identify any Eligible Costs for which Transporter has
sought recovery from a third party.