Dauphin Island Gathering Partners

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/16/1999, Docket: CP98- 6-003, Status: Effective

Original Sheet No. 236 Original Sheet No. 236 : Effective

 

 

20. REQUESTS FOR ADDITIONAL FACILITIES/EXPANDED CAPACITY

 

20.1 Shipper may request, by use of the Service Request Form, the addition of facilities to (or

connecting to), or expansion of, Transporter's MP Facility or Transporter's DI Facility to

allow the requesting Shipper to deliver/receive specified gas quantities under an existing

or new Transportation Service Agreement.

 

20.2 Transporter shall determine the following information in response to the above request:

 

(a) the estimated cost of constructing and installing the requested additional

facilities or modifying existing facilities ("New Facilities Cost") and an

estimated time to accomplish such; and,

 

(b) assess the impact of the requested additional facilities or modified existing

facilities on Transporter's ability to operate its system and continue to provide

service pursuant to then existing Transportation Service Agreements.

 

20.3 If Transporter's assessment of the impact to its system is not negative, then based on the

New Facilities Cost, if the requesting Shipper continues to desire to have the additional

facilities added to Transporter's MP Facility or Transporter's DI Facility or existing

facilities modified, the requesting Shipper and Transporter shall then execute the

documents required to implement the requested service - new or amended Transportation

Service Agreement, amended Exhibit "A", etc.

 

20.4 The provisions of this Section 20 shall not apply to the expansion of Transporter's MP

Facility or Transporter's DI Facility which would require Transporter to obtain additional

authority from the Commission.

 

20.5 Transporter shall submit an invoice to the requesting Shipper in the amount of the

estimated New Facilities Cost. Shipper shall make payment to Transporter pursuant to

the provisions of Section 14.2 of these General Terms and Conditions.

 

20.6 Transporter shall commence to construct and install the requested additional facilities or

modify existing facilities upon receipt of the payment pursuant to Section 20.5.