party or parties requesting additional facilities,
including but not limited to lateral lines, and any
pipeline interconnects, shall pay all costs for the
construction and installation, including all costs
involved in the filing of applications, pursuing
approvals and obtaining all licenses and permits
(including environmental) required for construction of
facilities or implementation of services, and any amounts
necessary to reimburse any costs, including any income
taxes that may be incurred by Transporter as a result of
construction contributions.
15.5 RESPONSIBILITIES OF INTERCONNECTING PARTY - Unless
otherwise agreed by Transporter, a party requesting the
addition of facilities to connect Gas supply or delivery
facilities or a party requesting an interconnection with
existing or proposed pipeline facilities will be
responsible for installing, maintaining, and operating
the necessary metering and regulating facilities,
including emergency flow control equipment, all of which
must be acceptable to Transporter. Metering and
regulating facilities are to be installed at a location
which, in Transporter's reasonable judgment, is
practical, convenient and readily accessible. The
interconnecting party shall provide the exhibits
necessary to support any needed Commission filings, or
permits required by any other governmental agency. The
interconnecting party must execute an interconnection
agreement with Transporter prior to the commencement of
any construction or service.