Effective Date: 03/27/2000, Docket: RP00-503-000, Status: Effective
First Revised Sheet No. 60 First Revised Sheet No. 60 : Effective
Superseding: Sub Original Sheet No. 60
32.3Applicability: This Section is applicable to any
Shipper who has a Service Agreement under Rate
Schedule FT-1 contained in this FERC Gas Tariff and
who elects to release, subject to the Capacity
Release Program set forth herein, all or a portion
of its transportation rights. Shippers under Rate
Schedules FT-1 shall be permitted to release their
capacity on a temporary or permanent basis, in
accordance with this Section. Capacity which may
be assigned to the Replacement Shipper hereunder
shall be limited to the firm capacity reserved by
the Releasing Shipper, as defined by the primary
Points of Receipt and the primary Points of Delivery
contained in the released capacity. Releases may be
made on an interruptible (i.e., subject to recall)
or firm basis and may be billed by Crossroads based
on usage.
Crossroads shall continue to sell its unsubscribed
firm capacity by providing notice of the availability
of such capacity on Crossroads' EBB System or by using
any other marketing service at its disposal.
Crossroads' EBB will also provide the capability for
any Potential Replacement Shipper to post its offer to
purchase capacity.
The maximum rate that may be paid for released
capacity shall be the applicable maximum tariff
rate; provided, however, that until September 30,
2002, the maximum rate ceiling does not apply to
capacity release transactions of less than one year.
32.4 Notice Requirement: A Shipper that desires to release any
or all of its firm capacity under this Section must notify
Crossroads electronically, in accordance with the time
schedule set forth in this Article 32, of its intent to
release capacity and the terms of the release.
(a) Shipper's notice shall include the following
information:
(1) Releasing Shipper's contract number and rate
schedule;
(2) the specific quantity of capacity to be
released;
(3) term of availability;
(4) if the request for release is on a permanent
basis;
(5) The Points of Receipt and Points of Delivery
at which Releasing Shipper will release capacity
and the quantity of capacity to be released at
each point;
(6) rates;
(7) whether the capacity will be firm or
recallable;