27. CONSTRUCTION OF FACILITIES
27.1 Arrangement for Construction of Transmission Facilities. Shipper may request Transporter to
construct, maintain and operate, either all or a part of, the lateral line for the transportation of gas from
Transporter's main transmission line to Shipper's markets, or when the delivery point to Shipper at
Transporter's main transmission line is in close proximity to a compressor station of Transporter, Shipper may
request Transporter to provide facilities to deliver gas to Shipper in excess of Transporter's main line
operating pressure. If Transporter shall determine that the granting of such request by Shipper is necessary
or desirable, that no undue burden will thereby be placed upon Transporter, and that no impairment of
Transporter's ability to render adequate service to its shippers will result therefrom, Transporter will
construct or provide such facilities if it can obtain proper, necessary authorization.
27.2 Method of Payment.
(a) In the event Transporter shall provide a lateral line or other transmission facilities at
the request of Shipper, unless otherwise agreed, Shipper will pay Transporter for the costs of such facilities
by paying in addition to the amount paid for natural gas, a facility charge consisting of the sum of the
following components:
(1) Depreciation computed at the annual accrual rates being used by Transporter for
booking depreciation expense applicable to such facilities;
(2) Return computed at the latest rate allowed Transporter by Federal Energy Regulatory
Commission in a formal rate determination applied to the original cost of the facilities less accrued
depreciation and plus necessary working capital applicable to such facilities;
(3) Taxes paid for the ownership and operation of such facilities; and
(4) Operation and maintenance expenses applicable to such facilities.
(b) The annual amount of the facility charge shall be established starting with the first day of
the calendar month in which Transporter shall have completed or made available for operation the facilities
requested by Shipper. Such amount shall be estimated by Transporter when the facilities are made available
and at the beginning of each calendar year thereafter, unless otherwise agreed. Each month, Transporter will
bill Shipper for one-twelfth of the estimated annual facility charge. An adjustment will be made if necessary
at the end of each calendar year to reflect the cost applicable to said facilities for the year.
27.3 Agreement. In each case where Transporter agrees to construct facilities at the request of the
Shipper, unless otherwise agreed, the Service Agreement will contain as an Exhibit thereto an agreement