9.1 Receipt and Delivery Quantities. If Shipper does not accept the

quantity nominated by Shipper at the Delivery Point on any day or days,

then Transporter may refuse to receive gas from Shipper at the Receipt

Point on such day or days. Transporter may refuse to deliver quantities to

Shipper at the Delivery Point if Shipper should be unable to provide the

equivalent quantities to Transporter at the Receipt Point.

 

9.2 Daily Rates of Flow. The gas to be transported hereunder shall be

received and delivered at uniform hourly and daily rates of flow as nearly

as practicable, subject to the daily nominations as provided in Shipper's

applicable Rate Schedule and Section 6 hereof. It is recognized that due to

operating conditions, the quantities of gas received and delivered may not

be in balance on any one particular day. Transporter and Shipper shall

endeavor to keep such variance to a minimum.

 

9.3 Flow Control. Nothing contained herein or in Transporter's Rate

Schedules shall limit Transporter's right to operate flow control or other

equipment to require Shippers to remain precisely in balance as to receipts

and deliveries at any time. Failure by Transporter to operate flow control

or other equipment, or any allowance by Transporter of imbalances up to or

exceeding balancing limits shall not limit Transporter's right to require

Shippers to maintain strict balances or Transporter's right to operate flow

control or other equipment to require Shippers to remain precisely in

balance.

 

9.4 Hourly Flow. Transporter shall have the right but not the obligation

to mutually agree with any Shipper to an hourly flow rate at any receipt

and/or delivery point(s) identified in the Rate Schedule FT-1 pro forma

service agreement that is different than the even hourly flow rate required

by Section 9.2 above. In the event that Transporter and Shipper mutually

agree to such an hourly flow rate, the hourly flow rate will be specified

in the pro forma service agreement in the blank space provided. Transporter

shall have the right to install flow control or other equipment to ensure

compliance with the hourly flow rate agreed to by Transporter and Shipper

under this Section 9.4.