Crossroads Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/23/2003, Docket: RP00-333-003, Status: Effective
First Revised Sheet No. 124 First Revised Sheet No. 124 : Effective
Superseding: Substitute Original Sheet No. 124
GENERAL TERMS AND CONDITIONS
(Continued)
(b) Priority Secondary Receipt Points Under Rate Schedule FT-1. For
capacity at secondary receipt points within the Primary Path under the FT-1
Rate Schedule, Transporter shall allocate capacity among Shippers on a pro
rata basis, based upon those Shippers' respective nominated quantities.
The priority for capacity at secondary receipt points within the Primary
Path shall apply where Shipper’s aggregate receipts at primary and
secondary receipt points do not exceed Shipper’s Transportation Demand.
(c) Secondary Receipt Points Under Rate Schedule FT-1. For receipts
from secondary receipt points under the FT-1 Rate Schedule outside the
Primary Path, Transporter shall allocate capacity among Shippers on a pro
rata basis, based upon those Shippers' respective nominated quantities. The
priority for receipts at secondary receipt points outside of the Primary
Path shall apply where Shipper’s aggregate receipts at primary and
secondary receipt points do not exceed Shipper’s Transportation Demand.
(d) Rate Schedule IT-1 And Overrun Quantities Under Rate Schedule FT-
1. Transporter shall allocate capacity in the manner set forth at Section
7.2(d) above.
(e) Receipt Points Under the IPP and PALS Rate Schedules. If there
is insufficient capacity to satisfy all nominations at a receipt point,
including nominations under IPP or PALS, Transporter shall allocate
capacity first to nominations under Rate Schedule IPP, then, if capacity is
still available, to nominations under Rate Schedule PALS. If there is
insufficient capacity to satisfy all IPP and PALS nominations, such
nominations shall be rejected, and holders of rejected nominations for IPP
and PALS service will be notified so that they can (i) arrange for or
implement a transfer between pools pursuant to the IPP Rate Schedule; (ii)
arrange for an inventory transfer pursuant to Section 18 (Transfers of
Imbalance Netting and Trading) of the General Terms and Conditions; (iii)
arrange for a predetermined allocation method (PDA) pursuant to Section 8.2
(Receipt Point Allocation) of the General Terms and Conditions; (iv)
renominate directly from such receipt point (and not from the IPP pool); or
(v) make other arrangements agreed to by Transporter.