(b) Secondary Delivery Points Under Rate Schedule FT-1. For deliveries to secondary delivery

points under the FT-1 Rate Schedule, Transporter shall allocate capacity among Shippers on a pro rata basis,

based upon those Shippers' respective nominated quantities. The priority shall apply where Shipper's

aggregate deliveries at primary and secondary delivery points do not exceed Shipper's Transportation Demand.

 

(c) Rate Schedule IT-1 and Overrun Quantities Under Rate Schedules FT-1.

 

(1) Where requested deliveries at the same highest rate exceed available capacity,

Transporter shall allocate capacity first to those Shippers flowing gas on a pro rata basis, based

upon respective confirmed nominations; and second to all remaining Shippers based upon the order in

which Transporter received nominations from those Shippers (equally to any Shippers submitting

nominations on the same day).

 

(2) If intraday nominations require an allocation of the pipeline system, the following

will describe the circumstances that allow a higher priority service to bump a lower priority

service.

(a) Evening Nomination Cycle: For nominations received by 6:00 p.m. CT and to

be effective at the start of the upcoming gas day, nomination increases at a primary point

under Rate Schedule FT-1 will not bump nominations at a secondary point under this same rate

schedule that are submitted and scheduled within the Timely Nomination Cycle. Nomination

increases submitted under Rate Schedule FT-1 whether at primary or secondary points will have

priority over nominated and scheduled quantities under Rate Schedule IT-1 and overruns under

the firm rate schedule and may bump such quantities effective at 9:00 a.m. CT the next day.

Nomination increases submitted under Rate Schedule IT-1 and overruns under the firm rate

schedules shall be subject to available unscheduled capacity and will not bump scheduled

quantities. Transporter shall notify Shippers being bumped as a result of intraday

nominations by 10:00 p.m. C.T.