GENERAL TERMS AND CONDITIONS
(Continued)
(d) Where discrepancies in quantities exist between confirming parties, the confirmed quantity
shall be determined as follows:
(1) With respect to the Timely Nomination Cycle, in the absence of agreement to the
contrary, the lesser of the confirmation quantities should be the confirmed quantity. If there is no
response to a Request for Confirmation or an unsolicited Confirmation Response, the lesser of the
confirmation quantity or the previously scheduled quantity should be the new confirmed quantity.
(2) With respect to increases during the Evening Nomination Cycle, Intraday 1 Nomination
Cycle and Intraday 2 Nomination Cycle, in the absence of agreement to the contrary, the lesser of the
confirmation quantities should be the new confirmed quantity. If there is no response to a Request
for Confirmation or an unsolicited Confirmation Response, the lesser of the confirmation quantity or
the previously scheduled quantity should be the new confirmed quantity.
(3) With respect to decreases during the Evening Nomination Cycle, Intraday 1 Nomination
Cycle and Intraday 2 Nomination Cycle, in the absence of agreement to the contrary, the lesser of the
confirmation quantities should be the new confirmed quantity, but in any event no less than the
elapsed-prorated-scheduled quantity. If there is no response to a Request for Confirmation or an
unsolicited Confirmation Response, the greater of the confirmation quantity or the elapsed-prorated-
scheduled quantity should be the new confirmed quantity.
(4) If there is no response to a request for confirmation or an unsolicited confirmation
response, Transporter shall provide Shipper with the Scheduled Quantities the following information
to explain why the nomination failed, as applicable:
(i) Transporter did not conduct the confirmation;
(ii) Upstream Confirming Party did not conduct the confirmation;
(iii) Upstream Service Requester did not have the gas or submit the nomination;
(iv) Downstream Confirming Party did not conduct the confirmation;
(v) Downstream Service Requester did not have the market or submit the
nomination.
(e) When a Shipper has more than one receipt point or more than one delivery point, such Shipper
shall specify in its nomination the supply reduction priorities and delivery reduction priorities (Priority
Reduction List) to be utilized at the receipt points or delivery points in the event of a loss of volume at
the receipt points or delivery points. If Shipper fails to provide a Priority Reduction List, Transporter may
deem the Shipper's nomination to be zero (0).